Physics 2009 JAMB Past Questions - Question 16: If a load of mass 10N stretches a cord by 1.2cm, what is the total work done?

Choose the correct answers from the options given.
If a load of mass 10N stretches a cord by 1.2cm, what is the total work done?
A:
B:
C:
D:
Examkits App

Examkit's JAMB CBT App

Practice JAMB offline with our Online, PC and Mobile App

  • ✅ 25+ years of past questions (2000 to 2025)
  • ✅ Video solutions and explanation to questions
  • ✅ E-library
  • ✅ Study by topic
  • ✅ And more.

Correct Answer

A

Explanation

Work done on a stretched cord
= Average force x extension
= 1×10×0.0122

= 6.0 x 10^−2J